Action Plan


2010

January, 2010 LOI Off-line Experiments (visit plan)



2009

March, 2009 Buck Regulator repaired
October, 2009 LOI Off-line Experiments (visit plan)

2007-2008

May-June, 2007 LOI Off-line Experiments
January 3-20, 2008 LOI Off-line Experiments (visit plan)
January 18, 2008 12th Collaboration Meeting at Cosener's House
May-June, 2008 LOI Off-line Experiments (visit plan)
August, 2008 LOI Off-line Experiments (visit plan)

2006-2007

provisional plan in 2006 and 2007, as of December 2006.

December 14-24, 2006 2nd Harmonic Physics Run
February 7-23, 2007 LOI Off-line Experiments
February 14, 2007 10th Collaboration Meeting with Videolink between RAL and ANL

2006-2007

provisional plan in 2006 and 2007, as of February 2 2006.

May-July, 2006 Hall 2 refurbishment
August, 2006 Move LOI to Hall 2
December-March, 2007 LOI Off-line Experiments


2003

October shutdown 2 sets of 2nd harmonic system will be installed

2004

March/25-August/25 Full sets(4 sets) will be complete
April-December LOI preparations at the MICE Hall ( provisional timetable, as of Oct 14 2004)
September Commissioning with 4 sets will start
Xmas LOI test will be started at the earliest case, which will continue for 2-3 physics runs.


It is understood that this schedule will depend on the operation periods of ISIS and could be drastically changed as operational necessity demands.
These dates are the best estimates at the present time.