| Status of major works | |||||
| Status | |||||
| Items of works | Finished | In progress | Scheduled | ||
| Construction and extension of buildings | X | ||||
| Modification of RFQ/IH linac | X | ||||
| Installation of: | |||||
| RFQ/IH linac | X | ||||
| charge breeder | X | ||||
| rf power supplies | X | ||||
| magnet power supplies | X | ||||
| cooling water circulators | X | ||||
| Assembly of beam transport sections | X | ||||
| Piping for cooling water | X | ||||
| Wiring for: | |||||
| rf power supplies | X | ||||
| magnet power supplies | X | ||||
| cooling water circulators | X | ||||
| control system | X | ||||
| Test for: | |||||
| rf tuning of cavities | X | ||||
| high power aging of cavities | X | ||||
| beam acceleration | X | ||||
| Last updated. August 3, 2004. | |||||